[ovs-dev] OVN 20.12 Soft Freeze
Mark Michelson
mmichels at redhat.com
Thu Nov 5 19:10:43 UTC 2020
Hi everyone,
According to the calendar in OVN's release documentation, tomorrow, 6
November, is supposed to be the soft freeze for OVN 20.12. However,
since there was no announcement made on the list about it, we decided in
today's IRC meeting to push the soft freeze back one week to 13 November
instead.
To refresh everyone, any new features that are desired to be in OVN
20.12 need to be submitted to the mailing list by then. They do not
necessarily need to be merged; they just need to be on the list. Hard
freeze and branch creation will follow 2 weeks from soft freeze on the
27 of November, with a scheduled release of 11 December.
Thanks,
Mark Michelson